Ten beds for people with dual diagnosis in Haut-Ittre. It opened in January 2023, following a construction project that nearly never came to fruition.
What it is.
A home established as part of La Maisonnée’s residential services for ten of the most vulnerable individuals: those with an intellectual disability combined with a mental illness.
The sixteen spots reported by Constellations include these ten spots and six spots in supported housing, which Constellations also helped establish.
The sixteen spots reported by Constellations include these ten spots and six spots in supported housing, which Constellations also helped establish.
Dual diagnosis is the situation in which it is most difficult to find a place. Facilities for people with intellectual disabilities refer them to psychiatric services, while psychiatric services refer them back to disability services. Families, meanwhile, have nowhere to turn.
A four-year project.
The project was selected by the Walloon Region following a call for proposals issued by the AViQ, which was a prerequisite for receiving operating subsidies.
Construction began in December 2019 and progressed rapidly. Then the general contractor went bankrupt as a result of the COVID-19 crisis. The contract was terminated before the bankruptcy was declared, thereby avoiding any financial impact.
Next, here’s a recap: AViQ approval for urgent work in March 2021, a new mandatory call for bids for the completion of the project, exterior work completed in the fall of 2021, followed by interior work. Provisional acceptance in June 2022; opening in January 2023.
The lead architect’s plans had to be redrawn, the contractor went bankrupt, the bidding process had to start over, and budget negotiations were tough. The house opened anyway.