House approved or under construction

CREB Woluwe

houses no. 12 and 13 of Constellations

82 places

Planned opening: fin 2028

Maquette Formatis CREB Woluwe

The most ambitious project ever undertaken by Constellations. Fifty-five places in the day center and twenty-seven in residential centers for children with severe physical and intellectual disabilities.

Why is this construction project necessary?

The current facilities were built without any government funding. They are unsanitary, contain asbestos, and are too small to meet standards.

The administration is requiring an expansion and a complete renovation, or else the center will be forced to close. This is therefore not a project aimed at improvement: the center’s very survival is at stake, and with it, the care of the children and the jobs of more than 120 people.

What will be built.

Renovation of the ground floor with the addition of one more story. Approximately 1,000 m² of additional space, allowing the restrooms and guest rooms to be brought up to code. The work will be carried out in phases: it is not possible to close the facilities during construction.

How is it funded?

The CREB Woluwé is the most ambitious project Constellations has ever supported. The significant increase in construction costs and the additional requirements for bringing the facility up to code necessitated an exceptional financial commitment.

COCOF provides a large portion of the funding. Constellations has also secured support from numerous foundations and private donors, including Anber, Lokumo, the Rotary Clubs of Brussels, Mr. M. Delacroix, CAP48, ROGER DE SPOELBERCH, NIF, Michelham, the 6088 Fund, and the ICB Foundation.

In response to rising costs, Constellations has increased its own contribution, bringing its total commitment to 850,000 euros, thanks in large part to the generosity of private donors.

The 2025 theater evening also helped support this project.

Seven years of efforts.

After seven years of administrative procedures and fundraising efforts, the project to rebuild and expand the CREB Woluwé has now been definitively approved.

The building permit was obtained after eighteen months of proceedings. Since the competitive bidding process resulted in proposals that exceeded the available budget, a negotiated procedure was used to select a contractor and bring the cost of the work down to an acceptable level.

The Cabinet gave its final approval in early July 2026, removing the last administrative obstacle to the project’s implementation.

Construction began on November 4, 2026. Work will proceed while the center remains open, with the new facilities scheduled to open in late 2028.

Seven years. That number says more than anything else about what it takes to build a shelter in Belgium.

Video

Photos

Practical information

See also

Other houses in Brussels

  • House approved or under construction

    ATIPI

    Watermael-Boitsfort, 20 places

  • House approved or under construction

    FARILU

    Watermael-Boitsfort, 25 places

  • Planned house

    Nido

    Haren, 30 places

See all houses

Act with us

Every gesture can open a door

Constellations funds and builds care homes for people with an intellectual disability, in Belgium.